Abstract
Probable Maximum Precipitations and Floods (PMPs/PMFs) are the hydrological loading criteria for contemporary dam/reservoir design and operation and maintenance (O&M) inspection programs. These parameters are dynamic and strictly desirable for safety of high hazardous infrastructure. The spillway safety rule and protocol are being tightened over the years. This study evaluates the overtopping hazards/potentials of both Air Itam (1962, 5.6 km2) and Teluk Bahang (1999, 10 km2) dams using three sets of PMP series (1) coastal PMP set (SMHB 1992,1994) adopted mainly in the past design studies, (2) current update and results of a nationwide PMP study by NAHRIM in 2008, and (3) PMPs with incorporation of an adjustment factor to account for climate change scenario by NAHRIM in 2013. This study has demonstrated primarily inadequate spillway capacity for Air Itam dam which was designed in the 1960’s without the benefit of adequate spillway sizing based on recent PMP/PMF methodology. Under both recent PMP/PMF loadings derived from a nationwide study (NAHRIM 2008) and climate change (NAHRIM 2013) scenarios, the existing morning glory spillway is inadequate for safe passage of PMP/PMF. It is recommended that retrofitting the existing spillway capacity should be considered as an urgent matter. Teluk Bahang dam designed and built in the late 1990’s was deemed adequate in its spillway capacity conforming to the contemporary PMP/PMF foresight. The dam is equipped with provision of ample headroom and anti-cavitation measures as additional margin of safety.
References
Afrooz, A. H., Akbari, H., Rakshandehroo, G. R., & Pourtouiserkani, A. (2005). Climate change impact on probable maximum precipitation in Chenar-Rahdar river basin. In Water Management 2005 (pp. 36–47). ASCE Conference.
Al-Maimum, A., & Hashim, A. (2004). Generalized long duration probable maximum precipitation isohyetal map for Peninsular Malaysia. Journal of Spatial Hydrology, 4(1), 212–234.
Australian Bureau of Meteorology. (2003). The estimation of probable maximum precipitation in Australia: Generalized short-duration method. Bureau of Meteorology, Melbourne, Australia.
Australian Bureau of Meteorology. (2009). Climate change and probable maximum precipitation (HRS Report No. 12). Bureau of Meteorology, Melbourne, Australia.
Chen, X., Hossain, F., & Leung, L. R. (2017). Probable maximum precipitation in the U.S. Pacific Northwest in a changing climate. Water Resources Research, 53(11), 9600–9622. https://doi.org/10.1002/2017WR021094
Chow, V. T., Maidment, D. R., & Mays, L. (1988). Applied hydrology. McGraw-Hill, New York, NY.
Coleman, S. E., Andrews, D. P., & Webby, M. G. (2002). Overtopping of non-cohesive homogeneous embankment. Journal of Hydraulic Engineering, 128(9), 829–830. https://doi.org/10.1061/(ASCE)0733-9429(2002)128:9(829)
Desa, M. N., & Rakhecha, P. R. (2007). Probable maximum precipitation for 24-h duration over an equatorial region: Part 2 – Johor, Malaysia. Atmospheric Research, 84(1), 84–90. https://doi.org/10.1016/j.atmosres.2006.06.005
Desa, M. N., Noriah, A. B., & Rakhecha, P. R. (2001). Probable maximum precipitation for 24 h duration over Southeast Asia monsoon region: Selangor, Malaysia. Atmospheric Research, 58(1), 41–54. https://doi.org/10.1016/S0169-8095(01)00070-9
Government of India. (2021). Guidelines for Selecting and Accommodating Inflow Design Floods for Dams. Central Water Commission Central Dam Safety Organisation. Dam Safety Rehabilitation Directorate, New Delhi, India. Doc. No. CDSO_GUD_DS_06_v1.0.
Heng, H. H., & Hii, C. P. (2011). A review on PMP estimation in Malaysia. International Journal of Hydrology Science and Technology, 1(1), 63–87.
Heng, H. H., & Hii, C. P. (2013a). Risk assessment scenario of Machap Dam overtopping using new Malaysian PMP series. Jordan Journal of Civil Engineering, 7(1), 101–110.
Heng, H. H., & Hii, C. P. (2013b). A case study on dam overtopping under different PMP scenario. UNIMAS e-Journal of Civil Engineering, 4(1), 40–49.
Heng, H. H., Hii, C. P., & Kho, K. T. (2013). An assessment of Bengoh Dam overtopping scenarios. Geomatics, Natural Hazards and Risk. https://doi.org/10.1080/19475705.2013.781547
Heng, H. H., Hii, C. P., & Pan, W. F. (2016b). A tale of two dams under extreme weather in Upper Langat River Basin. SEGi Journal of Engineering and Technological Advances, 1(1), 5–25.
Heng, H. H., Hii, C. P., Pan, W. F., & Choo, C. M. (2016a). Hydrological risk assessment: A comparison of morning glory spillway capacity. SEGi Journal of Engineering and Technological Advances, 1(1), 59–74.
Heng, H. H., Pan, W. F., & Chan, J. A. (2025). Dam break event modelling and case study: A co-relationship between breach discharges and dam physical parameters in Malaysia. SEGi Journal of Engineering and Technological Advances, 10(1), 151–170. https://doi.org/10.35934/segi.v10i1.123
Husain, M., Nadya, S., & Chia, F. J. (2014). Estimating probable maximum precipitation for Linau River Basin in Sarawak. Journal of Civil Engineering, Science and Technology, Sarawak, Malaysia. https://doi.org/10.33736/jcest.138.2014
Jothiyangkoon, C., Hirunteeyakul, C., Boonrawd, K., & Sivapalan, M. (2013). Assessing the impact of climate and land use changes on extreme floods in a large tropical catchment. Journal of Hydrology, 490, 88–105. https://doi.org/10.1016/j.jhydrol.2013.03.036
Khoo, F. W. L., Law, P. L., Lai, S. H., Onn, Y. W., & Ting, H. S. (2009). Quantitative dam break analysis on a reservoir earth dam. International Journal of Environmental Science and Technology, 6(2), 203–210. https://doi.org/10.1007/BF03327623
Koutsoyiannis, D. (1999). A probabilistic view of Hershfield’s method for estimating probable maximum precipitation. Water Resources Research, 35(4), 1313–1322. https://doi.org/10.1029/1999WR900002
Kunkel, K. E., Karl, T. R., Esterling, D. R., Redmond, K., Young, J., Yin, X., & Hennon, P. (2013). Probable maximum precipitation and climate change. Geophysical Research Letters, 40, 1402–1408. https://doi.org/10.1002/grl.50334
Lagos-Zunifa, M. A., & Ximena-Vargas, M. (2014). PMP and PMF estimations in sparsely gauged Andean basins and climate change projections. Hydrological Sciences Journal, 59(11), 2027–2042. https://doi.org/10.1080/02626667.2013.877588
Lee, J., Choi, J., Lee, O., Yoon, J., & Kim, S. (2017). Estimation of probable maximum precipitation in Korea using a regional climate model. Water, 9, 240. https://doi.org/10.3390/w9040240
Micovic, Z., Schaefer, M. G., & Taylor, G. H. (2015). Uncertainty analysis for probable maximum precipitation estimates. Journal of Hydrology, 521, 360–373. https://doi.org/10.1016/j.jhydrol.2014.12.033
NAHRIM. (2008). Derivation of probable maximum precipitation for design floods in Malaysia (TRP No. 1). Ministry of Natural Resources and Environment, Kuala Lumpur, Malaysia.
NAHRIM. (2013). Estimation of future design rainstorm under the climate change scenario in Peninsular Malaysia (Technical Guide No. 1). National Hydraulic Research Institute of Malaysia, Kuala Lumpur, Malaysia.
National Academies of Science. (2024). Modernizing Probable Maximum Precipitation Estimation of Probable Maximum Precipitation.
NK/SMHB. (2000). Pahang–Selangor raw water transfer project engineering services and detailed engineering design: Hydrograph final report. JBA & JKR, Malaysia.
Nor Eliza, A., & Takara, K. T. (2013). Estimating the probable maximum precipitation of Kuala Lumpur, Malaysia and Yodo River Basin, Japan using statistical methods. Journal of Disaster Research, 8(1), 197–206.
NZCOLD. (2023). Dam safety guidelines. New Zealand Society on Large Dams. ISBN: 978-0-473-69764-8.
Paramasivam, R., Alias, N.E., & Lokoman, R.M. (2023). Validation of Hershfield probable maximum precipitation estimation using homogeneous region in Malaysia. IC-ENSURES-2022 IOP Conf. Series: Earth and Environmental Science, 1143 012009. IOP Publishing. https://doi.org/10.1088/1755-1315/1143/1/012009
Perbadanan Bekalan Air Pulau Pinang (n.d.). Perbadanan Bekalan Air Pulau Pinang. Retrieved January 23, 2025. From Perbadanan Bekalan Air Pulau Pinang (PBA)
Phillips, R. V. C. (1976). Report of inspection of Ayer Itam Reservoir. Penang Water Authority, Georgetown, Pulau Pinang.
Rousseau, A. N., Klein, I. M., Freudiger, D., Gagnon, P., Frigon, A., & Ratte-Fortin, C. (2014). Development of a methodology to evaluate probable maximum precipitation (PMP) under changing climate conditions: Application to Southern Quebec, Canada. Journal of Hydrology, 519, 3094–3109. https://doi.org/10.1016/j.jhydrol.2014.10.053
Sarkar, S., & Maity, R. (2020). Estimation of Probable Maximum Precipitation in the context of climate change. MethodX, 7. https://doi.org/10.1016/j.mex.2020.100904
Sidek, L. M., Mohd Nor, P. R., Rakhecha, P. R., Basri, H., Jayothisa, W., Muda, R. S., Ahmad, M. N., & Abdul Razad, A. Z. (2013). Probable maximum precipitation (PMP) over mountainous region of Cameron Highlands–Batang Padang catchment of Malaysia. IOP Conference Series: Earth and Environmental Science, 16, 012049. https://doi.org/10.1088/1755-1315/16/1/012049
SMHB. (1992). Study on comprehensive water resources planning and development in the State of Pahang. Malaysia: Economic Planning Unit.
SMHB. (1994). Study on comprehensive water resources planning and development in the State of Johor. Malaysia: Economic Planning Unit.
SMHB/RB/JPZ. (2000). National water resources study 2000–2050. Malaysia: Economic Planning Unit.
SSP/SMHB. (1997). Kelantan River flood mitigation project: Feasibility study. Malaysia: Jabatan Pengairan dan Saliran.
Subramanya, K. (2008). Engineering hydrology (3rd ed.). India: Tata McGraw-Hill.
Taylor, M. A. W., & Toh, Y. K. (1976). Design flood hydrograph estimation for rural catchments in Peninsular Malaysia (Hydrological Procedure No. 11). Jabatan Pengairan dan Saliran, Ministry of Agriculture, Malaysia.
Thepprasit, C., Intavong, A., Chompuchan, C., Chulee, N., & Sittichok, K. (2024). Spillway capacity estimation using flood peak analysis and probable maximum flood method. Water, 16, 1717. https://doi.org/10.3390/w16121727
Tingsanchali, T., & Tanmanee, S. (2012). Assessment of hydrological safety of Maei Sruai Dam, Thailand. Procedia Engineering, 32, 1198–1204. https://doi.org/10.1016/j.proeng.2012.02.077
Vischer, D. L., & Hager, W. H. (1988). Dam hydraulics. John Wiley & Sons, New York, NY.
WMO. (1986). Manual on estimation of probable maximum precipitation (Operational Hydrology Report No. 332). World Meteorological Organization, Geneva.
WMO. (2009). Manual on estimation of probable maximum precipitation (Operational Hydrology Report No. 1045). World Meteorological Organization, Geneva.
Yiau, S. S., & Putuhena, F. J. (2011). Probable maximum precipitation (PMP) analysis for Bakun Dam area. Journal of Civil Engineering, Science and Technology, 2(2), 53–59. https://doi.org/10.33736/jcest.95.2011
Yigzaw, W., Hossain, F., & Kalyanapu, A. (2013). Comparison of PMP-driven probable maximum floods with increasingly urbanized catchment: The case of American River watershed. Earth Interactions, 17(8), 1–18. https://doi.org/10.1175/2012EI000497.1